1. Earned Value Management Tutorial Module 2: Work Breakdown Structure
  2. Prepared by:
  3. Module 2: Work Breakdown Structure
  4. What is a Work Breakdown Structure?
  5. What is a Work Breakdown Structure?
  6. What is a Work Breakdown Structure?
  7. Why is a Work Breakdown Structure needed?
  8. Preparing a WBS
  9. Preparing a WBS
  10. Preparing a WBS
  11. Current Project WBS Project WBS Needed
  12. Not Planned to this level
  13. Preparing a WBS
  14. Current Project WBS Project WBS Needed
  15. Preparing a WBS
  16. Current Project WBS Project WBS Needed
  17. Preparing a WBS
  18. Preparing a WBS
  19. Preparing a WBS
  20. Building a WBS
  21. WBS: Structure
  22. WBS: Structure
  23. WBS: Structure
  24. WBS: Structure
  25. WBS: Structure
  26. Work Breakdown Structure (WBS) Tree
      1. 1 ACME Housing Corporation
      2. 1.1 New Home Construction
      3. 1.1.1 Concrete
      4. 1.1.1.1 Pour Foundation 1.1.1.2 Install Patio
      5. 1.1.1.3 Pour Stairway 1.1.2 Framing
      6. 1.1.5 Interior
      7. 1.1.5.1 Install Drywall 1.1.5.2 Install Carpets 1.1.5.3 Painting
      8. 1.1.6 Roofing
      9. 1.1.6.1 Install Felt 1.1.6.2 Install Shingles 1.1.6.3 Install Vents
  27. WBS and Earned Value
  28. WBS Dictionary
  29. Organization Breakdown Structure (OBS )
  30. Responsibility Assignment Matrix (RAM)
  31. Responsibility
  32. Assignment Matrix Responsibility
  33. Assignment Matrix
  34. Responsibility Assignment Matrix (RAM)
  35. Responsibility Assignment Matrix (RAM)
  36. Responsibility Assignment Matrix (RAM)
  37. Review of Module 2
  38. Summary of Module 2

Earned Value Management Tutorial
Module 2: Work Breakdown Structure

Back to top


Prepared by:

Module 2 – Work Breakdown Structure
1
Prepared by: Booz Allen Hamilton

Back to top


Module 2: Work Breakdown Structure
Welcome to Module 2. The objective of this module is to introduce you to Work
Breakdown Structure (WBS) and other supporting documents.
This module will include defining and illustrating the following topics:
• Work Breakdown Structure
• WBS dictionary
• Organizational Breakdown Structure (OBS)
• Responsibility Assignment Matrix (RAM)

Module 2 – Work Breakdown Structure
2
Prepared by: Booz Allen Hamilton

Back to top


What is a Work Breakdown Structure?
Planning a project using earned value management is no different than the
initial planning necessary to implement any given project. There are basic
items that you need to know and understand as a project manager:
– What makes up my entire project (Scope)?
• What is the agreed upon work scope and what is additional work?
– What are my start and completion dates (Schedule)?
– How much is the project going to cost (Cost)?
Over the years, it was determined that project managers needed a tool to help
capture and control their project scope. This led to the development of a
Work Breakdown Structure (WBS).
On the following pages we will define and discuss a WBS
.

Module 2 – Work Breakdown Structure
3
Prepared by: Booz Allen Hamilton

Back to top


What is a Work Breakdown Structure?
The Work Breakdown Structure (WBS) is a tool that defines a project and
groups the project’s discrete work elements in a way that helps organize and
define the total work scope of the project. A WBS element may be a product,
data, a service, or any combination. WBS also provides the necessary
framework for detailed cost estimating and control along with providing
guidance for schedule development and control. Additionally the WBS is a
Each descending level of the
WBS represents an increased
level of detailed definition of the
project work. As you can see in
this WBS for developing the
BEST Management Book, the
work is broken down into all the
discrete elements of work, the
total sum of which represents
all the work and products
necessary to produce the book.
dynamic tool and can be revised and updated as
needed by the project manager.
Project
Selec t ion
1.1. 1.1. 1
Project
Organization
1.1. 1.1. 2
Project
Planning
1.1. 1.1. 3
Chapter 1
1.1.1.1
Budget &
Cost
1.1. 1.2. 1
Scheduling
1.1.1. 2.2
Project
Contr ols
1. 1.1. 2.3
Auditing
1. 1.1. 3.1
A dministrative
Closeout
1. 1.1. 3.2
W riting
Text Book
1. 1.1
Editing
Text Book
1.1. 2
Publishing
Text Book
1.1. 3
Project Ma nageme nt
- An Introduction
1.1
BEST Manageme nt
Books
1.
Chapter 2
1.1.1.2
Chapter 3
1.1.1.3
Editing
Chapter 1
1.1.2.1
Editing
Chapter 2
1.1.2.2
Editing
Chapter 3
1.1.2.3
Project
Selec t ion
1.1. 1.1. 1
Project
Organization
1.1. 1.1. 2
Project
Planning
1.1. 1.1. 3
Chapter 1
1.1.1.1
Budget &
Cost
1.1. 1.2. 1
Scheduling
1.1.1. 2.2
Project
Contr ols
1. 1.1. 2.3
Auditing
1. 1.1. 3.1
A dministrative
Closeout
1. 1.1. 3.2
W riting
Text Book
1. 1.1
Editing
Text Book
1.1. 2
Publishing
Text Book
1.1. 3
Project Ma nageme nt
- An Introduction
1.1
BEST Manageme nt
Books
1.
Chapter 2
1.1.1.2
Chapter 3
1.1.1.3
Editing
Chapter 1
1.1.2.1
Editing
Chapter 2
1.1.2.2
Editing
Chapter 3
1.1.2.3

Module 2 – Work Breakdown Structure
4
Prepared by: Booz Allen Hamilton
Project
Selection
1.1.1.1.1
Project
Orga ni za ti on
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Auditing
1.1.1.3.1
A dministrative
Clos eout
1.1.1.3.2
Writing
Text Book
1.1.1
Edit ing
Text Book
1.1.2
Publishing
Text Book
1.1.3
Project Ma nageme nt
- An Introduction
1.1
BEST Manageme nt
Books
1.
Chapter 2
1.1.1.2
Chapter 3
1.1.1.3
Editing
Chapter 1
1.1.2.1
Edit ing
Chapter 2
1.1.2.2
Edit ing
Chapter 3
1.1.2.3
Project
Selection
1.1.1.1.1
Project
Orga ni za ti on
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Auditing
1.1.1.3.1
A dministrative
Clos eout
1.1.1.3.2
Writing
Text Book
1.1.1
Edit ing
Text Book
1.1.2
Publishing
Text Book
1.1.3
Project Ma nageme nt
- An Introduction
1.1
BEST Manageme nt
Books
1.
Chapter 2
1.1.1.2
Chapter 3
1.1.1.3
Editing
Chapter 1
1.1.2.1
Edit ing
Chapter 2
1.1.2.2
Edit ing
Chapter 3
1.1.2.3

Back to top


What is a Work Breakdown Structure?
After reviewing the WBS on the previous page, an important point needs to be
reviewed. Although a WBS can be depicted so as to look like an
organizational chart, it
IS NOT
an organizational chart.
Remember the WBS defines a
project and groups the project
elements for managing a
project. An organizational chart
describes the project team that
will accomplish the project.

Module 2 – Work Breakdown Structure
5
Prepared by: Booz Allen Hamilton

Back to top


Why is a Work Breakdown Structure needed?
Not all projects have a WBS, and it is true that some of these projects have been
successful. So why is a WBS needed? We have already looked at a few
reasons, but in review, the WBS:
– Provides a framework for organizing and managing the approved project
scope
– Helps ensure you have defined all the work that makes up the project
– Provides a framework for planning and controlling cost and schedule
information
– It’s better to be deliberate about planning than rely on luck!
Additionally, when you work for a company or organization that has many
projects being performed simultaneously, each of the projects is competing for
the limited resources available. The WBS enables you to review project
details and distinguish one project’s needs from others within the company or
organization. Why is distinguishing one project from another important? It
enables you to identify resource requirements and allocate resources more
effectively.
Now let’s look at preparing a WBS.

Module 2 – Work Breakdown Structure
6
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
In preparing a WBS there are a number of steps that need to be taken to make
sure the WBS developed will help manage your project. Below and on the
following pages we will discuss these steps.
1. Identify final project products necessary for achieving project success. The
WBS should assist the project manager in developing a clear vision of the
end product. You need to answer the following question:
– What must be delivered to achieve project success?
• You may need to review the project scope documents for guidance.
2. Identify the major deliverables necessary for project success.
– These are items that by themselves do not satisfy the project need but
combined make up a successful project
– Examples: a design completion, generator delivery, or acceptance
test completion
– In the DOE, these could be Critical Decisions (see DOE Order 413.3)

Module 2 – Work Breakdown Structure
7
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
3. Incorporate additional levels of detail until management requirements for
managing and controlling the project are met.
– Remember that each project is different, thus each WBS will be
different
– WBS’s from previous projects can be used as templates, but
remember that the management philosophy and the level of details
may be different from project to project
– Understand your controlling and reporting requirements
• Projects have different requirements; make sure you take these
into consideration when developing low level details
4. Review and refine the WBS until the stakeholders agree with the level of
project planning and reporting.
– Remember that no matter how detailed a WBS is, there are planning
and reporting restrictions a WBS creates. On the following pages, we
will look at examples of these restrictions.

Module 2 – Work Breakdown Structure
8
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
Let’s use the BEST Management Books’ WBS we looked at earlier. Assume
that the WBS was only planned down to the chapters level (see graph
below, left), but after the first month of work, the stakeholder wants reporting
at the subchapter level (see graph below, right). Without restructuring the
WBS and changing the other supporting systems, like cost tracking and
reporting, it is impossible for the project manager to meet the stakeholder
s
request.
Project
Selection
1.1.1.1.1
Project
Organization
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Project
Selection
1.1.1.1.1
Project
Organization
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Chapter 1
1.1.1.1
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Chapter 1
1.1.1.1
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2

Back to top


Current Project WBS
Project WBS Needed

Back to top


Not Planned to this level

Module 2 – Work Breakdown Structure
9
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
Now let’s reverse the situation. Assume WBS was planned down to the
subchapter level (see graph below, left), but after the first month of work, the
stakeholder wants reporting at the chapter level (see graph below, right). Is
there any restructuring needed to the WBS? The answer is “No”. Since you
planned the work at a level below what is now the stakeholder’s
requirement, you can “roll-up” and meet the stakeholder’s request.
Do you still see a problem with the project WBS? Let’s take a look.
.
Project
Selection
1.1.1.1.1
Project
Organization
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Project
Selection
1.1.1.1.1
Project
Organization
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Chapter 1
1.1.1.1
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Chapter 1
1.1.1.1
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2

Back to top


Current Project WBS
Project WBS Needed

Module 2 – Work Breakdown Structure
10
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
Actually, there is not a problem with the WBS structure, but a problem with the
idea of time and cost. The project manager spent time and resources to
define the WBS down to a level that he determined was appropriate. The
only benefit could be that the project manager wishes to manage the
project at the lower level and will roll-up reporting for the stakeholder.
In review, always get stakeholders to agree with the level of project planning
and reporting.
Project
Selection
1.1.1.1.1
Project
Organization
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Project
Selection
1.1.1.1.1
Project
Organization
1.1.1.1.2
Project
Planning
1.1.1.1.3
Chapter 1
1.1.1.1
Budget &
Cost
1.1.1.2.1
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.2.3
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Chapter 1
1.1.1.1
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2
Chapter 1
1.1.1.1
Writing
Text Book
1.1.1
Chapter 2
1.1.1.2

Back to top


Current Project WBS
Project WBS Needed

Module 2 – Work Breakdown Structure
11
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
In developing a WBS, one must realize that there are multiple ways to develop
a WBS for any given project. Some ways might be better than others, but
the two most important items to remember are that the WBS must contain
all approved scope and the Project Manager must develop the WBS to
reflect the way he/she intends to manage the project.
Other items to consider when developing a WBS are:
• Reporting requirements
• Size of project
• Resource executing the work (contractors vs. in-house)
• Complexity of the project
On the following two pages are examples of alternative WBS structures for
the BEST Management Books project.

Module 2 – Work Breakdown Structure
12
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
This WBS structure is designed to control scope
by chapters, unlike the original WBS which
was developed to control scope by writing
and editing.

Module 2 – Work Breakdown Structure
13
Prepared by: Booz Allen Hamilton

Back to top


Preparing a WBS
This WBS structure is taking into consideration
that the writing and editing will be executed
by a contractor. It still requires the contractor
to control scope by writing and editing by
chapter.

Module 2 – Work Breakdown Structure
14
Prepared by: Booz Allen Hamilton

Back to top


Building a WBS
Armed with the basics of the WBS, it is time to examine them in more detail and
to begin to understand how to build one. To do this, let’s look at building a
WBS for the construction of a single family home. First, take a moment to
familiarize yourself with some background information about the construction
company, which appears on the next page.

Module 2 – Work Breakdown Structure
15
Prepared by: Booz Allen Hamilton

Back to top


WBS: Structure
The ACME Housing Corporation, which you own, has been contracted to build
its first house. You want to be able to manage your projects effectively and
efficiently, so you charge your project managers to develop an appropriate
WBS. You decide to manage the project by the individual tasks necessary to
complete the house.
You hope that this is the first of many houses that ACME will build, so you start
the WBS with ACME in the highest position, or Level 1. Accordingly, Level 1
is given a WBS code of 1. You assign the WBS code of 1 to the highest level
because all future projects (houses) will be summarized at Level 1
.
Level 1
㼀㼀㼀㼀
NOTE: For ease of explanation, our
example will assume the following:
• Design is complete
• All permits issued
• All Material ordered
• Inspection happens

Module 2 – Work Breakdown Structure
16
Prepared by: Booz Allen Hamilton

Back to top


WBS: Structure
With Level 1 established, you can begin to complete the WBS. But what should
the next level be?
The logical next level for ACME is the project level. Level 2 is the level for each
individual project, or house, that ACME undertakes. As the chart shows
below, Level 2 is identified at the project level: House.
Appropriately, the code for Level 2 corresponds to Level 1. In this case, the
code is 1.1.
Level 1
㼀㼀㼀㼀
Level 2
㼀㼀㼀㼀

Module 2 – Work Breakdown Structure
17
Prepared by: Booz Allen Hamilton

Back to top


WBS: Structure
Now the WBS for the housing project is complete, right? Actually, no, the WBS
is not complete. At this point you determine that you want to divide the work
into the major elements needed to build a house. You choose to divide Level
3 into six elements: concrete, framing, plumbing, electrical, interior and
roofing. You realize that these are both major deliverables and milestones for
managing the project. They also enable you to get to your goal of managing
the project by task.
Notice the WBS codes at level 3. Each is unique to the project and starts with
the WBS code from the level above (1㼀1.1㼀1.1.1). Now lets look and see
if another level is needed.
Level 1
㼀㼀㼀㼀
Level 2
㼀㼀㼀㼀
Level 3
㼀㼀㼀㼀

Module 2 – Work Breakdown Structure
18
Prepared by: Booz Allen Hamilton

Back to top


WBS: Structure
The ACME WBS is taking shape, but it does not quite define the project at a
level that shows needed tasks for completion. To do this, one more level
needs to be included.
Level 4 of the WBS will enable us to manage
the project as desired. All of our contractors
fit into specific elements at level 4, and so
do all specific departments. As with the
previous Levels, note the WBS codes that
have been assigned to the tasks and their
relationship to the previous Level
.
Level 4
㼀㼀㼀㼀
Level 3
㼀㼀㼀㼀
㼀㼀㼀㼀
Level 1
㼀㼀㼀㼀
Level 2

Module 2 – Work Breakdown Structure
19
Prepared by: Booz Allen Hamilton

Back to top


WBS: Structure
What do you think? Is the WBS complete? Does it enable the manager to
manage at the task level?
After a review to make sure that only approved scope is included, our WBS is
complete. It does include the necessary components to manage the project
by task.

Module 2 – Work Breakdown Structure
20
Prepared by: Booz Allen Hamilton

Back to top


Work Breakdown Structure (WBS) Tree
The graphical structure of the WBS is an easy
way to identify the project components and
relationships of those components;
however, the WBS can be displayed in
another format as well: the Tree format.
Both formats are acceptable. The graphical
format is at times easier to understand, but
can take up considerable space in a report.
The tree is not as easy to understand but is
more easily incorporated into a report
format.
Note the WBS codes and the structure of the
Levels in the Tree format mirror the
graphical format. The content has not
changed; only the way the content is
presented has changed.
1 ACME Housing Corporation
1.1 New Home Construction
1.1.1 Concrete
1.1.1.1 Pour Foundation
1.1.1.2 Install Patio
1.1.1.3 Pour Stairway
1.1.2 Framing
1.1.2.1 Frame Exterior Walls
1.1.2.2 Frame Interior Walls
1.1.2.3 Install Roofing Trusses
1.1.3 Plumbing
1.1.3.1 Install Water Lines
1.1.3.2 Install Gas Lines
1.1.3.3 Install B/K Fixtures
1.1.4 Electrical
1.1.4.1 Install Wiring
1.1.4.2 Install Outlets/Switches
1.1.4.3 Install Fixtures
1.1.5 Interior
1.1.5.1 Install Drywall
1.1.5.2 Install Carpets
1.1.5.3 Painting
1.1.6 Roofing
1.1.6.1 Install Felt
1.1.6.2 Install Shingles
1.1.6.3 Install Vents

Module 2 – Work Breakdown Structure
21
Prepared by: Booz Allen Hamilton

Back to top


WBS and Earned Value
Now that you understand the WBS and how to assemble one, let’s examine
how it relates to earned value.
In Module 1, we discussed that in implementing earned value, a project
manager must have control of the project’s “triple constraint” (scope,
schedule and cost). Unlike traditional management, which tracks two
components (budget and expenditures), earned value considers three and
provides a more robust understanding of a project’s overall progress and
health.
The WBS is the most important item in defining and controlling the project
scope. How does it control the scope? If the WBS is not developed correctly
and does not capture all the project scope and only the project scope, then
the “earned value” system built using the WBS will be inaccurate. The project
manager will lose control of the project before it even begins.
Now that you have your WBS, let’s take a look on the next page at the other
item needed to properly organize your project.

Module 2 – Work Breakdown Structure
22
Prepared by: Booz Allen Hamilton

Back to top


WBS Dictionary
Once the WBS is complete
,
the WBS dictionary needs to be the next item
developed. The WBS dictionary is a narrative documentation of the effort
needed to accomplish all work defined in the WBS. The WBS dictionary is
developed for the lowest level element in the WBS only.
To better understand how a WBS and a WBS dictionary work, let
s compare it
to a book and the book’s table of contents:
– The WBS is the table of contents for the project. It captures the
contents in an organized fashion (chapters, subchapter).
– The WBS dictionary is the book itself. It tells the story. In our case the
story is what work will be accomplished and what outputs will be
produced in each of the WBS elements. The total of these descriptions
is how a house will be built and what is needed to build the house.
The WBS dictionary will often lead to the development of the statements of
work (SOW) for the project. SOWs will be discussed in later modules.

Module 2 – Work Breakdown Structure
23
Prepared by: Booz Allen Hamilton

Back to top


Organization Breakdown Structure (OBS
)
Now that our WBS is developed, the appropriate resources and responsibilities
need to be assigned. The first step in doing this is developing the
Organizational Breakdown Structure (OBS) for the project. The OBS
indicates the organizational relationships and is used as the framework for
assigning work responsibilities. Below is an example of the OBS for the
ACME house building project. The OBS is structured by Responsible
Department and then by Performing Department at the lowest level. This
Performing Department level is where the responsibility and resource needed
to accomplish the project will be assigned.
With the relationships
and responsibilities
defined, the second
and final step is to
merge the WBS and
OBS. Take a look on
the next page.
CONCRETE
PERF DEPT 6010
M. Manning
MASONRY
PERF DEPT 6020
T. Greams
TEST
PERF DEPT 6030
K. Neumann
CIVIL
RESP DEPT
R. Kelly
CARPENTRY
PERF DEPT 5010
R. Sites
ROOFING
PERF DEPT 5020
Y. Taylor
DRYWALL
PERF DEPT 5030
D. Smith
STRUCTURAL
RESP DEPT
P. Tate
PERF DEPT 4010
S. Johnson
HOOKUP/TIE-IN
PERF DEPT 4020
P. Ottis
ELECTICAL
RESP DEPT
J. Sims
WATER/SEWER
PERF DEPT 3010
K. Wells
GAS
PERF DEPT 3020
R. Oriely
PLUMBING
RESP DEPT
R. Lee
PROJECT OFFICE
RESP DEPT
B. Smithers
WIRING

Module 2 – Work Breakdown Structure
24
Prepared by: Booz Allen Hamilton

Back to top


Responsibility Assignment Matrix (RAM)
Merging the WBS and OBS, the project manager creates a Responsibility
Assignment Matrix (RAM). The RAM displays the lowest level of both the
WBS and the OBS. The integration identifies specific responsibility for

Back to top


Responsibility

Back to top


Assignment Matrix
Responsibility

Back to top


Assignment Matrix
CONCRET E
PERF DEPT 6010
M. Manning
MASONRY
PERF DEPT 6020
T. Greams
TES T
PERF DEPT 6030
K. Neumann
CIVI
L
RESP DEPT
R. Kelly
CARPENTRY
PERF DEPT 5010
R. Sites
ROOFING
PERF DEPT 5020
Y. Taylor
DRYW
ALL
PERF DEPT 5030
D. Smith
STRUCTURAL
RESP DEPT
P. Tate
PERF DEPT 4010
S. Johnson
HOO
KUP/T
I
E-I
N
PERF DEPT 4020
P. Ottis
EL
ECT
ICAL
RESP DEPT
J. Sims
WATER/S EW ER
PERF DEPT 3010
K. Wells
GAS
PERF DEPT 3020
R. Oriely
PLUMBING
RESP DEPT
R. Lee
PROJ ECT OFFICE
RESP DEPT
B. Smithers
WIRING
CONCRET E
PERF DEPT 6010
M. Manning
MASONRY
PERF DEPT 6020
T. Greams
TES T
PERF DEPT 6030
K. Neumann
CIVI
L
RESP DEPT
R. Kelly
CARPENTRY
PERF DEPT 5010
R. Sites
ROOFING
PERF DEPT 5020
Y. Taylor
DRYW
ALL
PERF DEPT 5030
D. Smith
STRUCTURAL
RESP DEPT
P. Tate
PERF DEPT 4010
S. Johnson
HOO
KUP/T
I
E-I
N
PERF DEPT 4020
P. Ottis
EL
ECT
ICAL
RESP DEPT
J. Sims
WATER/S EW ER
PERF DEPT 3010
K. Wells
GAS
PERF DEPT 3020
R. Oriely
PLUMBING
RESP DEPT
R. Lee
PROJ ECT OFFICE
RESP DEPT
B. Smithers
WIRING
specific project tasks. It is at this
point that the project manager
develops control accounts or work
package. Control accounts and
work packages will be discussed
in Module 4. Lets look at what the
RAM may look like on the ACME
house construction project on the
next page.

Module 2 – Work Breakdown Structure
25
Prepared by: Booz Allen Hamilton

Back to top


Responsibility Assignment Matrix (RAM)
Below is part of the RAM for the ACME housing project.
– The lowest level of the WBS appears across the top
– The lowest level of the OBS appears on the vertical axis
An “X” appears at the intersection of the WBS task and OBS personnel. The “X”
defines the specific performing department (from the OBS) assigned to
complete a task (from the WBS).
Performing Dept.
Manager
Pour
F oundat ion
1.1.1.1
Install Patio
1.1.1. 2
Pour
Stairway
1. 1.1.3
Frame
Exterior
Walls
1.1.2.1
Frame
Interior
Walls
1.1. 2.2
Install
Roofing
Trusse
1.1.2.3
In s tall
Water
Lines
1.1.3. 1
Install Gas
Lines
1. 1.3.2
Install B/K
Fixt ures
1.1.3.3
CONCRETE
DEPT 6010
Manning
X
X
X
MASONRY
DEPT 6020
Greams
X
TEST
DEPT 6030
Neumann
X
X
X
CARPENTRY
DEPT 5010
Sites
X
X
X
ROOFI NG
DEPT 5020
Taylor
X
DRYWALL
DEPT 5030
Smith
X
WIRING
DEPT 4010
Johnson
HOOKUP/TIE-IN
DEPT 4020
Ottis
WATER/SEWER
DEPT 3010
Wells
X
X
GAS
DEPT 3020
Oriely
X
X
1.1.3
PLU MBI NG
CONCRETE
1.1. 1
FRA MIN G
1.1.2

Module 2 – Work Breakdown Structure
26
Prepared by: Booz Allen Hamilton

Back to top


Responsibility Assignment Matrix (RAM)
To better understand the RAM, consider the ACME housing project.
The OBS specifies Mr. Sites and the carpentry department as responsible for
framing the exterior walls. Therefore, in the RAM, an X appears at the cross-
section between the task, framing the exterior walls, and the responsible party,
Mr. Sites. Additionally, Mr. Sites is also responsible for framing the interior
walls and installing the roofing trusses
.
Performing Dept.
Manager
Pour
F oundat ion
1.1.1.1
Install Patio
1.1.1. 2
Pour
Stairway
1. 1.1.3
Frame
Exterior
Walls
1.1.2.1
Frame
Interior
Walls
1.1. 2.2
Install
Roofing
Trusse
1.1.2.3
In s tall
Water
Lines
1.1.3. 1
Install Gas
Lines
1. 1.3.2
Install B/K
Fixt ures
1.1.3.3
CONCRETE
DEPT 6010
Manning
X
X
X
MASONRY
DEPT 6020
Greams
X
TEST
DEPT 6030
Neumann
X
X
X
CARPENTRY
DEPT 5010
Sites
X
X
X
ROOFI NG
DEPT 5020
Taylor
X
DRYWALL
DEPT 5030
Smith
X
WIRING
DEPT 4010
Johnson
HOOKUP/TIE-IN
DEPT 4020
Ottis
WATER/SEWER
DEPT 3010
Wells
X
X
GAS
DEPT 3020
Oriely
X
X
1.1.3
PLU MBI NG
CONCRETE
1.1. 1
FRA MIN G
1.1.2

Module 2 – Work Breakdown Structure
27
Prepared by: Booz Allen Hamilton

Back to top


Responsibility Assignment Matrix (RAM)
Alternatively, hours and dollars may be used in the RAM rather than an “X”.
Using our ACME House example, the “X” was replaced with the hours
needed to complete the task. Now we see that Mr. Sites has 300 hours to
frame the exterior walls, 250 hours to frame the interior walls and 175 hours
to install the roofing trusses.
Performing Dept.
Manager
Pour
Foundation
1.1.1.1
Install Patio
1.1.1.2
Pour
Stairway
1.1.1.3
Frame
Exterior
Walls
1.1.2.1
Frame
Interior
Walls
1.1.2.2
Install
Roofing
Trusse
1.1.2.3
Install
Water
Lines
1.1.3.1
Install Gas
Lines
1.1.3.2
Install B/K
Fixtures
1.1.3.3
CONCRETE
DEPT 6010
Manning
200
125
85
MASONRY
DEPT 6020
Greams
50
TEST
DEPT 6030
Neumann
20
10
5
CARPENTRY
DEPT 5010
Sites
300
250
175
ROOFING
DEPT 5020
Taylor
100
DRYWALL
DEPT 5030
Smith
275
WIRING
DEPT 4010
Johnson
HOOKUP/TIE-IN
DEPT 4020
Ottis
WATER/SEWER
DEPT 3010
Wells
100
15
GAS
DEPT 3020
Oriely
125
25
1.1.3
PLUMBING
CONCRETE
1.1.1
FRAMIN G
1.1.2

Module 2 – Work Breakdown Structure
28
Prepared by: Booz Allen Hamilton

Back to top


Review of Module 2
Take some time to review the major items of this module:
• The Work Breakdown Structure (WBS) is a tool that defines a project and
groups the projects elements in a way that helps organize and define the
total work scope of the project
• In preparing a WBS there are a number of steps that need to be taken
including:
– identifying the final project product
– identifying the major deliverables
– incorporating the appropriate levels of detail
– obtaining stakeholder agreement
• WBS Dictionary is a narrative description of the lowest level for each WBS
element
• Organizational Breakdown Structure (OBS) indicates the organizational
relationships and is used as the framework for assigning work
responsibilities
• Responsibility Assignment Matrix (RAM) merges the WBS and OBS to
identify the specific responsibility for specific project tasks

Module 2 – Work Breakdown Structure
29
Prepared by: Booz Allen Hamilton

Back to top


Summary of Module 2
At this point we have examined the WBS, OBS and RAM. These items are the
start for laying the groundwork for developing an earned value management
system (EVMS). In the next module you will examine these item in more
detail by looking at the development of the project schedule.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics for developing a WBS, OBS and
RAM
This concludes Module 2.

Back to top